10 March → 14 March 2025

Tree Removals Including Stump Grinding

31 March → 27 June 2025

Phase 1 - Talbot to Victoria

Road reconstruction, including replacement of sewers and watermain.

02 July → 31 October 2025

Phase 2 - Victoria to John

Road reconstruction, including replacement of sewers and watermain.