Elk Street Reconstruction Update: July 9, 2025

Elk Street Reconstruction Update: July 9, 2025

The Elk Street reconstruction project is progressing to the next phase. As a part of the Phase 2 construction, a connection to the John Street South watermain is required.

Location: Elk Street and John Street South Intersection

Schedule: Tentative Start Date - Monday, July 14, 2025
Anticipated Completion - Wednesday, July 16, 2025

Scope: Installation of watermain and restoration of intersection

Contractor: PV-EX Construction Ltd.

Impacts During Construction:

  • Traffic: To facilitate a safe work environment during trenching activities, John Street South will be limited to one lane of flagged traffic. A minimum of one lane of flagged traffic will be provided at all times. The intersection will be restored with base asphalt upon completion of the works.

Lane Closure on John Street South

Share Elk Street Reconstruction Update: July 9, 2025 on Facebook Share Elk Street Reconstruction Update: July 9, 2025 on Twitter Share Elk Street Reconstruction Update: July 9, 2025 on Linkedin Email Elk Street Reconstruction Update: July 9, 2025 link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>