Elk Street Reconstruction Update: July 9, 2025
Elk Street Reconstruction Update: July 9, 2025
The Elk Street reconstruction project is progressing to the next phase. As a part of the Phase 2 construction, a connection to the John Street South watermain is required.
Location: Elk Street and John Street South Intersection
Schedule: Tentative Start Date - Monday, July 14, 2025
Anticipated Completion - Wednesday, July 16, 2025
Scope: Installation of watermain and restoration of intersection
Contractor: PV-EX Construction Ltd.
Impacts During Construction:
- Traffic: To facilitate a safe work environment during trenching activities, John Street South will be limited to one lane of flagged traffic. A minimum of one lane of flagged traffic will be provided at all times. The intersection will be restored with base asphalt upon completion of the works.

Share Elk Street Reconstruction Update: July 9, 2025 on Facebook
Share Elk Street Reconstruction Update: July 9, 2025 on Twitter
Share Elk Street Reconstruction Update: July 9, 2025 on Linkedin
Email Elk Street Reconstruction Update: July 9, 2025 link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends