Elk Street Reconstruction Update: July 16, 2025

Elk Street Reconstruction Update: July 16, 2025

Work Completed to Date

Phase 1

  • Sanitary line, storm line and watermain from Talbot Street to Victoria Street have been installed
  • Road base has been brought close to final grade with granular material and compacted
  • Curb and gutter installations have commenced

Phase 2

  • Construction of Elk Street has begun between Victoria Street and John Street South
  • Asphalt pulverization, saw cutting and removal of private driveways/curbs and gutters
  • Temporary waterline installation is underway to each residential property

Work Scheduled for the Next Weeks

Phase 1

  • Continuing with installation of curb and gutter, sidewalk/multi-use pathway
  • Preparation of road base for base asphalt followed by placement of base asphalt

Phase 2

  • Asphalt pulverization, saw cutting and removal of private driveways/curbs and gutters
  • Continuing with installation of temporary waterline to each residential property

Road Closures and Access

  • Elk Street will be closed to through traffic during construction, but open to local traffic
  • Driveway access may be interrupted periodically during construction. Notification will be provided in advance of any prolonged driveway access disruptions.

Phase 1

  • Local residence East of work area, access from Talbot Street
  • Local residence West of work area, access from Victoria Street

Phase 2

  • Local residence East of work area, access from Victoria Street
  • Local residence West of work area, access from John Street South

Elk Street New Curb and Gutter


Construction Safety

  • Your safety is very important to us. Please respect the work zone.
  • Please use caution when using the street or sidewalks near the construction limits.
  • Maintain a safe distance from any moving equipment, stockpiles or trenches.